REMINDER: New lanes of I-465,  Allisonville Road ramp scheduled to open this weekend 

Lane and ramp restrictions needed to complete traffic switch

As a reminder, Clear Path crews are planning to open five miles of new travel lanes on eastbound I-465 from the White River to Fall Creek Road in northeast Indianapolis this weekend. The ramp from Allisonville Road to eastbound I-465 is also expected to open by Sunday, June 7. 

The new eastbound I-465 lanes include the final two remaining bridges in the I-69/I-465 interchange.   Lane and ramp closures are scheduled to allow crews to safely shift traffic.

Drivers can expect the following restrictions starting overnight Thursday: 

Thursday, June 4 at 9 p.m. to Friday, June 5 at 6 a.m.  

  • Ramp from southbound I-69 to southbound I-465 closed 
  • Ramp from southbound I-465 to 56th Street/Shadeland Avenue closed 
  • Ramp from 82nd Street to southbound I-465 closed 
  • Southbound I-69 reduced to two lanes from just north of 86th Street to the I-69/I-465 interchange 
  • Rolling slowdowns on eastbound I-465 over 75th Street

Friday, June 5 at 6 a.m. to Sunday, June 7 at 6 a.m. 

  • Ramp from southbound I-465 to 56th Street/Shadeland Avenue closed to traffic coming from eastbound I-465 

Friday, June 5 at 9 p.m. to Saturday, June 6 at 6 a.m

  • One lane closed on northbound I-465 between 75th Street and the White River

Friday, June 5 at 9 p.m. to Sunday, June 7 at 6 a.m. 

  • Ramp from eastbound I-465 to northbound I-69 closed 
  • Ramp from eastbound I-465 to southbound Binford Boulevard closed 
  • Ramp from eastbound I-465 to Allisonville Road closed 
  • Ramps from Keystone Avenue to eastbound I-465 closed 
  • Eastbound I-465 reduced to two lanes from Keystone Avenue to Fall Creek Road 

Delays are expected. Drivers should plan ahead and seek alternate routes, when possible. Actual dates and anticipated work may be adjusted if inclement weather or other unforeseen activities occur.  After the shift is complete, I-465 will be open to three lanes in each direction from the White River to Fall Creek Road. This will allow crews to complete final work on the project, including barrier wall removal, pavement restriping and noise barrier installation. By the end of 2026, I-465 is expected to open to four lanes in each direction.  

For schedule updates, follow the project on  Facebook,   X and   Instagram, and subscribe to email and text message alerts at  ClearPath465.com.    