Lane and ramp closures scheduled this week

Closures needed for barrier wall removal and signage removal, pavement striping

INDIANAPOLIS (Jan. 27, 2025) – This week, several lane and ramp closures will take place throughout the Clear Path project. The work this week will include single and double-lane closures that are necessary for barrier wall removal and signage removal, as well as pavement striping and repair. 

The schedule for this week’s closures is as follows, weather permitting:

Monday, January 27 (9 p.m. to 6 a.m.)

  • Two rolling slowdowns on I-465 southbound just south of 71st Street
  • Three lanes will remain open on I-465 southbound near 71st Street

Tuesday, January 28

  • Mobile pavement striping operation on I-465 eastbound between 82nd Street overpass and Binford Boulevard (9 a.m. to 3 p.m.)
  • Mobile pavement repair operation (9 p.m. to 6 a.m.)

Wednesday, January 29 (9 p.m. to 6 a.m.)

  • Ramp from I-465 eastbound to I-69 northbound closed
  • Ramp from I-465 eastbound to southbound Binford Boulevard closed
  • I-465 eastbound right lane closed near Allisonville Road
  • Three lanes will remain open on I-69 northbound from 82nd Street to 96th Street

Thursday, January 30 (9 p.m. to 6 a.m.)

  • Ramp from I-465 eastbound to I-69 northbound closed
  • Ramp from I-465 eastbound to southbound Binford Boulevard closed
  • Three lanes will remain open on I-465 northbound near Fall Creek

Actual dates and anticipated work may be adjusted if inclement weather or other unforeseen activities occur. 

For additional information and schedule updates, follow the project on  FacebookX and  Instagram and subscribe to email and text message alerts at  ClearPath465.com. To learn more about Indiana Safe Zones, including active locations and answers to frequently asked questions, visit SafeZonesIN.com


Read More Traffic & News Updates

Clear Path Quarterly

INDIANAPOLIS (Jan. 13, 2025) – Clear Path 465 wrapped up 2024 with some major progress! The project closed out the year by

Read More