I-69 South Ramp to I-465 South Closed Overnight Monday and Tuesday

Ramp Closure Needed to Place Bridge Beams

Starting Monday, September 16, at 9 p.m. Clear Path crews will begin setting beams for a new bridge that will be a part of I-465 East.

The overhead work will require the I-69 South to I-465 South ramp to be closed overnight.

Additionally, there will be several other ramp and lane closures throughout the Clear Path Corridor. The closure schedule is as follows:

Monday, September 16 (9 p.m. to 6 a.m.)

  • I-69 South to I-465 South ramp closed

Tuesday, September 17 (9 p.m. to 6 a.m.)

  • I-69 South to I-465 South ramp closed
  • 82nd St to I-69 North ramp closed
  • I-465 North to I-69 North ramp single lane closure

Wednesday, September 18 (9 p.m. to 6 a.m.)

  • I-69 South to I-465 South ramp single lane closure

As a reminder, Clear Path is in active construction. Please be sure to drive within the speed limit and keep our roads safe.

For schedule updates, follow the project on Facebook, X and Instagram and subscribe to email and text message alerts at ClearPath465.com.   


Read More Traffic & News Updates

Clear Path Quarterly

It’s a clear view of progress! Three new bridges and new roadway are now open to traffic! Two new bridges on I-465 West and one bridge on I-69 North opened over