82nd Street Ramps
I-69 Over 82nd Street
Mainline I-465
I-69 / I-465 Interchange
The first construction phase will rebuild and add lanes to 4.5 miles of I-465 between Fall Creek and the White River. INDOT awarded the first construction contract to a tri-venture of E&B Paving, Rieth-Riley Construction and Gradex in December 2021.
The second and final construction phase will focus on nearly two miles of I-69 and Binford Boulevard, including the 82nd Street and I-465 interchanges.
In early 2023, INDOT awarded the second construction contract to a tri-venture of E&B Paving, Rieth-Riley Construction and Gradex. Construction started for this phase of the project in early 2023.
Follow the progress of Clear Path 465 and receive project updates by email and text.
Sign up for Clear Path 465 email updates to get the latest information about the project delivered straight to your inbox.
Sign up for Clear Path 465 text updates to receive the latest news, information and more about the project.
Status: Complete and open to traffic


Status: Under Construction
All are on track for completion by late this year.
Status: Five of the 6 new bridges at 82nd Street are complete and open to traffic.
Open with limited access:
All bridges and ramps at 82nd Street are expected to open with full access by the end of 2026.
Status: Complete and open to traffic with limited access
82nd Street Exit Ramp
82nd Street to Southbound I-69 On-Ramp
Drivers are expected to regain access to westbound I-465 and Binford Boulevard from 82nd Street/southbound I-69 in late 2026.
Status: Open to traffic with limited access
82nd Street Exit Ramp
82nd Street to Northbound I-69 On-Ramp
Status: OPEN
Status: Open
The ramp from 56th Street to northbound I-465 opened in summer 2026, after northbound I-465 traffic was shifted into its final configuration.
Status: Closed
Status: Open





Status: Complete and open to traffic
Northbound and westbound I-465 is open to four lanes of traffic, but traffic is not yet in its final configuration.
Crews are moving barrier wall, installing pavement markings and preparing to move westbound I-465 into its final configuration.





Status: Complete and open to traffic


Status: Complete and open to traffic
Eastbound and southbound I-465 is in its final configuration with four mainline travel lanes, plus auxiliary lanes that expand the roadway to five or six lanes in some locations.
The speed limit on this portion of I-465 increased to 55 mph in mid-August 2026.
Status: Complete and open to traffic
Status: Under Construction
The Clear Path 465 Project Team performed a traffic noise impact analysis during project development. Under INDOT’s Noise Policy, seven noise barrier sections were identified as reasonable and feasible and will be built or relocated:
The noise barrier along northbound I-465 past 75th Street has been built, and the noise barrier along eastbound I-465 between 82nd Street and I-69 is under construction. Construction on the remaining noise barriers will continue through the end of the project, with road construction remaining the primary focus at this time.
Status: Complete and open to traffic


