Friday, March 13 ( 10 p.m. to 1 a.m.)
82nd Street Ramps
Click HERE to track progress and know what’s ahead in the latest Clear Path 465 Project Update.
I-465 Over 75th Street
I-465 Interchange
I-69 Bridges Over 82nd Street
The first construction phase will rebuild and add lanes to 4.5 miles of I-465 between Fall Creek and the White River. INDOT awarded the first construction contract to a tri-venture of E&B Paving, Rieth-Riley Construction and Gradex in December 2021.
The second and final construction phase will focus on nearly two miles of I-69 and Binford Boulevard, including the 82nd Street and I-465 interchanges.
In early 2023, INDOT awarded the second construction contract to a tri-venture of E&B Paving, Rieth-Riley Construction and Gradex. Construction started for this phase of the project in early 2023.
Follow the progress of Clear Path 465 and receive project updates by email and text.
Sign up for Clear Path 465 email updates to get the latest information about the project delivered straight to your inbox.
Sign up for Clear Path 465 text updates to receive the latest news, information and more about the project.
Status: Complete and open to traffic


Status: Complete and open to traffic
Status: Closed and under construction



Status: Five of the 6 new bridges at 82nd Street are complete and open to traffic. Some bridges are open with limited access.
Open with limited access:
All bridges and ramps at 82nd Street are expected to open with full access by the end of 2026.
Status: Complete and open to traffic with limited access
Drivers are expected to regain access to westbound I-465 and Binford Boulevard from 82nd Street/southbound I-69 in late 2026.
Status: Complete and open to traffic with limited access
Fully open
Open with limited access
Status: Closed
Status: Closed
Status: Closed
Status: Complete and open to traffic
Status: Under construction



Status: Complete and open to traffic





Status: Complete and open to traffic


Status: Complete and open to traffic
While westbound I-465 is complete, traffic is currently reduced to fewer lanes than drivers will have at the end of construction because eastbound I-465 traffic has been shifted to use these lanes while the eastbound lanes are being rebuilt.


Status: Complete and open to traffic
Status: Under Construction
The Clear Path 465 project team performed a traffic noise impact analysis during project development. Under INDOT’s Noise Policy, seven noise barrier sections were identified as reasonable and feasible and will be built or relocated:
A portion of the noise barrier along northbound I-465 past 75th Street has been built. Construction on the remaining noise barriers will continue through the end of the project, with road construction remaining the primary focus at this time.